Roughly 30 to 40% of off-plan projects in Phuket are handed over later than promised, with average delays running 6 to 12 months and, among smaller developers, sometimes stretching past 24 months6. Buyers usually discover this only after the deposit has cleared and the construction site is still empty. In 2026, dozens of residential schemes are rising simultaneously across the island, and the market is saturated with marketing promises that are not always backed by enforceable contracts.
The off-plan model itself is not the problem. The real risk sits inside how the Sale and Purchase Agreement (SPA) is structured, and what leverage a buyer retains over the developer once the first payment has been made. Below are the concrete risks, the checks worth running before you commit, and the questions investors most often ask before buying off-plan on the island.
A long-stop date (a fixed handover deadline with exit rights if missed) is the single most important protection in the SPA. Without it, a buyer has no legal lever against a delayed developer1
Calendar-based payment schedules, rather than milestone-based ones, effectively turn your instalments into an unsecured loan to the developer. If construction stalls, your money is already spent1
Peylaa Phuket (408 units, from 7.2 million THB) targets a Q4 2027 handover, but the full Autograph Collection hospitality infrastructure is not expected until 2030, a three-year gap between keys and services23
The InterContinental Branded Residences in Phuket is 50% sold across its 111 units, with completion slated for Q4 20274
Authorities halted construction on a beachfront project in Rawai over suspected encroachment on public land and a missing environmental review5
A wave of branded residence handovers is expected in 2027-2028, raising the risk of market oversupply and added pressure on already tight construction timelines
This is the most common mistake buyers make. A developer promises handover 'around Q4 2027' but the SPA never locks in a hard deadline with the buyer's right to terminate and get a refund if it slips. Without that clause, the buyer has no real legal standing1.
Mitigation: insist the SPA include a specific long-stop date, penalty clauses for breach, and a unilateral right of exit.
If your payment schedule is tied to dates ('six months after signing') rather than to completion of the foundation, frame, or roof, the developer collects your money regardless of actual progress on site. In effect, you are financing the developer with no security1.
Mitigation: push for every instalment to be linked to a verified construction milestone, ideally checked by an independent inspector.
Peylaa Phuket illustrates a recurring problem: residential units are due in 2027, while the Autograph Collection hotel and full hospitality infrastructure will not be operational until 20303. Three years without the promised services means weaker rental yields and management headaches for owners in the meantime.
Mitigation: clarify exactly which infrastructure will be functioning on the day you get your keys, and put it in writing in the contract.
In June 2026, Phuket authorities suspended construction of a beachfront project in Rawai following complaints from local residents and the sea gypsy community, amid concerns over encroachment on waterways and a missing Environmental Impact Assessment (EIA)5. Buyers who had already paid deposits before the investigation were left in limbo.
Mitigation: before putting down a deposit, verify the Chanote (land title deed), the building permit, and EIA status through an independent lawyer.
Many developers active in Phuket today are one or two-project outfits. If a developer has never successfully delivered a completed project, the risk of delay or an outright construction freeze rises sharply1.
Mitigation: ask for a list of completed projects, visit them in person, and talk to existing owners about their experience.
Even large developers flagged rising build costs in 2026 as a key risk factor2. If a developer raised insufficient capital early on, material cost inflation can force work stoppages or a downgrading of specifications.
Mitigation: review the project's financial model and ask whether a contingency reserve exists for unforeseen cost overruns.
2027-2028 will see several large branded residence projects complete at roughly the same time4. Excess supply can compress rental rates and complicate resale, which indirectly weighs on developer financial stability.
Mitigation: analyse not just your own project but the competing pipeline within a 5 km radius.
One practical safeguard worth knowing: for larger developments (over 80 units or above 4,000 sqm), buyers should independently verify EIA status with Thailand's Office of Natural Resources and Environmental Policy and Planning (ONEP) rather than relying on the developer's word7.
Need help with your case?
An expert will look at your situation and reply within 30 minutes during business hours.
A long-stop date is the final deadline by which the developer must hand over the property. If that date is missed, the buyer gains the right to terminate the contract and reclaim funds. Without this clause in the SPA, a buyer has no real legal mechanism to force action1.
Three steps matter most: (1) request the list of completed projects and inspect them in person; (2) check the company's incorporation documents through Thailand's Department of Business Development (DBD); (3) hire an independent lawyer to verify the Chanote, permits, and the SPA itself1.
The Bang Tao to Cherngtalay corridor is in the middle of a construction boom, which raises the risk of oversupply2. In Rawai, construction has been suspended on at least one project over land-related legal issues5. Risk exists in any district if the developer has not passed proper due diligence.
Check the SPA for a long-stop date and penalty provisions. Consult a Thai lawyer. File a complaint with the Office of the Consumer Protection Board (OCPB). If the developer is a foreign-owned entity, litigation can take years to resolve.
A recognised brand (Marriott, InterContinental) reduces reputational risk but does not guarantee on-time delivery. The brand operator is usually not the developer and carries no financial responsibility for the construction itself. Peylaa Phuket, for instance, is being built by Capstone Asset, not by Marriott3.
Only if the SPA explicitly spells out refund conditions for missed deadlines. Without a long-stop date and matching compensation clauses, a buyer risks losing the entire amount already paid.
A common structure is 10-30% at signing and in the following months, with the balance due at handover. Some developers, however, demand as much as 50-70% before construction is even finished. The more capital you transfer before completion, the greater your exposure.
Four documents matter most: (1) the Chanote, the land title deed; (2) the building permit; (3) the EIA (Environmental Impact Assessment), required for coastal or restricted-zone projects; (4) the SPA, with a long-stop date and milestone-linked payments.
Off-plan remains an attractive strategy: prices during construction typically run 15-25% below completed-unit pricing, according to market estimates. But this advantage only holds with a properly vetted developer and a tightly drafted contract. Skip the due diligence, and the discount can turn into a loss.
Source: The Phuket News
Ready to invest in Thailand property? Housebook's experts will shortlist projects and run the deal with you.
This material was prepared with the help of artificial intelligence. Please check key figures and terms with our adviser.
Was this article helpful?
Your mark is stored only in this browser.
Projects

from ฿350,000,000

from ฿100,700,000

from ฿16,000,000
Personalised selection
Answer 4 questions and we will prepare a personalised selection of property in Thailand.
Read also

Can foreigners own property in Thailand? Learn the 49% condo quota, 30-year leasehold rules, villa structures, and key risks for 2026 buyers.

How foreigners buy property in Thailand: freehold vs leasehold, the 49% condo quota, FET form, Land Department registration, risks and a 6-step timeline.

Does buying property in Thailand grant residency? Compare LTR, investment visas and Thailand Privilege, from 3M THB to 500,000 USD, for 2026 buyers.